Could you deliver 1,512 m2 of office space within just three weeks? Jan Snel did it with ease for Total Raffinaderij Antwerpen nv.
The temporary accommodation, which Total Refinery designated OPTARA, is intended for about two years’ use. The first phase of the project consisted of a large number of rooms: 35 offices and 4 blocks of sanitary facilities, as well as 3 staircases, 2 outside and 1 inside. The second phase of the project consisted of 82 units, all of which are used as offices.
The project was made of K1000 units and converted to EBB insulation standards. The temporary accommodation is also fully fire-resistant (RF60). Now, employees of the Total Refinery in Antwerp can make use of data and inverters on-site. Additionally, an HWA recovery system for flushing saves a lot of water from the sanitary facilities.